Concor Buildings was well positioned to take on the challenging construction of Oxfords Parks Phase I which commenced in February 2019 after their successful completion of the BP Building in 2018.
This phase comprises five buildings: four mixed-use premium office and retail buildings, and a fifth building which will house a hotel designed to 4-star standards with special emphasis on art and business.
Construction work of 6 Parks Boulevard (also known as the Arup Building) started in February 2019. Work on this structure is progressing according to schedule, in line with the handover end January 2020.
Initially designed as a three-storey structure with the ground floor being dedicated to retail space, these plans were modified to the requirements of the tenants, Arup and Sony. This resulted in another slab being added to accommodate a private entertainment area, as well as recording studios on the fourth level.
The structure on this rooftop level mimics the design shape of the building, but with a smaller footprint, thus occupying only about 50% of the available rooftop space. A double lift shaft arrangement was incorporated into the modified design to ensure that this level will only be accessible to authorised visitors.
A portion of the site is located directly above the Gautrain tunnel, necessitating 20% of the foundation for the basement to be a raft foundation as the bottom of the excavation was situated just above the Zone of Exclusion.
The rest of the foundation was constructed with traditional piles and pile caps. Concrete used in the construction of the basement levels was a standard 25MPa, while 30MPa concrete was specified for the floor slabs.
The visual impact of this building will be in the architectural façade where a special pattern was printed on the glass panels. This application will create a forest-like graphic, reinforcing the urban green theme of Oxford Parks. This paint technique will add aesthetic interest, but also yield thermal and anti-glare properties to address the green star requirements of the building.
Concor Buildings’ contract for this structure includes construction as well as the total fitting out of all services. Despite some unforeseeable delays during the construction of the basement, the schedule was back on track by the time the first-floor slab was cast and the team is confident that the building will be ready for occupation by the tenants in February 2020.
The building on 8 Parks Boulevard, or Building 3 as it is known on site, has recently been added to Concor’s portfolio in this precinct and is currently being constructed as a five-storey mixed-use office and retail facility. Construction is progressing well, and the first-floor slab is currently being cast.
The ground level of this building extends onto a cantilevered slab which forms the new Parks Boulevard, providing access to service and delivery vehicles. Both the Arup building and Building 3 face onto Parks Boulevard, which is currently presenting the contractor with an added challenge which requires meticulous planning of sequences for access of the various construction vehicles on this newly constructed cantilevered road.
The scope for Building 3 is to deliver the shell structure as future tenants will be involved in the fit-out of the building. The scheduled completion date is June 2020.
The building on the north-eastern corner of the precinct is also currently under construction and will be the new head office of Life Healthcare. Eighty per cent of the first-floor slab of the five-storey building has already been finished, on schedule for completion by October 2020. A common design protocol governs all these buildings, but this building will incorporate an auditorium, as specified by the tenant.
The fifth building, a Radisson Red hotel, has been designed as a seven-storey facility to 4-Star standards and will have 222 guest rooms. A gym and a swimming pool will occupy the roof terrace. The first two levels will be constructed using conventional slabs, with post-tensioned concrete being used from the third floor up. The hotel will be ready to accept guests at the beginning of 2021.
Oxford Parks Phase 1 is a testimony to meticulous coordination to ensure that the concurrent construction of the different buildings run smoothly. Three tower cranes are on site which necessitated a special resource-linked crane study to optimise rental time. The large workforce which is required for the simultaneous construction of the various structures of Phase 1 means that there can be no compromise on safety. Daily planning and safety meetings are held, with weekly review meetings taking place to ensure that progress remains on-schedule.
According to Martin Muller, the Concor Buildings contracts manager, being awarded Phase 1 of the Oxford Parks development is a direct result of Concor Buildings’ achievement during the construction of the BP Building, 199 Oxford Road, ahead of time and within budget.
Muller adds: “This project is significant for Concor Buildings particularly in the current suppressed trading conditions in the South African construction industry. Being appointed contractor on this prestigious and complex project is testimony to the company’s experience and expertise, coupled with a good relationship with the developer, Intaprop.”