THERE’S MORE TO TRANSFORMERS THAN MEETS THE EYE

While it might seem at first glance that there is little to distinguish one transformer from another in terms of design and construction (other than size), the differences can in fact be substantial and potential buyers need to be aware that there is certainly far more to a transformer than initially meets the eye.

David Claassen, managing director of Trafo Power Solutions, says that in order to make an informed decision as to which product will best meet the needs of a particular application, the customer will need to look at several factors, including the ambient temperature ranges in which the transformer will operate, the expected core and copper losses, the load conditions and the ability of the manufacturer to test products in accordance with appropriate standards.

“The minimum, maximum and average temperatures in which a transformer can safely operate will affect the design and consequently the price of a transformer,” he explains. 

In dry-type transformers, two main temperature winding insulation classes exist – namely Class F and Class H. Class F allows the transformer to operate safely at temperatures up to 155°C without damage while Class H allows the transformer to accommodate temperatures up to 180°C.

Claassen says another detail to look out for is that both oil-cooled and dry-type transformers are available in multiple cooling options. 

“The most common is natural air (AN), where the surrounding still air is used to keep the transformer operating within the correct temperature range. The second most common option is the forced air (AF) method, which entails moving air over the radiators, or over the core and windings. This allows the temperatures to be kept in check,” he explains. Transformers using forced cooling are able to supply additional load over and above the nominal power rating but it is important to rate the transformer at AN (natural ventilation) and use the fans as a temporary measure. 

With regard to transformer losses, these comprise two parts – load or core losses and no-load or copper losses. It is important to note that there are IEC standards set up as to what the maximum allowable load and no-load losses may be. The higher the transformers losses are, the cheaper it is to produce and the operational cost will be higher 

Also important is the load that the transformer will supply (or be supplied by). Unfortunately, with today’s modern grid there is no such thing as a perfect load. Power electronics, as well as many other switching electronics, have contributed to non-sinusoidal waveforms, and hence harmonics. The Total Harmonic Distortion (THD(i)) that a transformer encounters significantly influences the design of that transformer.

Finally, potential buyers need to look carefully at the quality control programmes manufacturers have in place. These will ensure that at all stages of manufacturing all raw materials and components can be tracked. 

SOLID FOUNDATION FOR DE WATERKANT HERITAGE PROJECT

Variable ground conditions at an upmarket mixed-use development in Cape Town has demanded some innovative solutions from contractor GVK-Siya Zama Construction and readymix specialist AfriSam.

At the Old Cape Quarter project in De Waterkant, four floors of luxury apartments are being added to retail and office space. This meant substantial strengthening of the foundations and columns to accommodate the increased load, according to Garth Robb, contracts director at GVK-Siya Zama Construction. This was not a straightforward process, says Robb, with insufficient space in the basement areas for normal class 3 formwork. 

“We made extensive use of biscuit columns, where we added reinforcing around the old existing columns and core-drilled at an angle from above – adding grout to beef up the column sizes,” he says. “We core-drilled through the base to transfer the load onto the piling, with a number of columns and bases needing to be demolished and reconstructed.”

A key complication was that concrete could only be poured manually into the biscuit columns by wheelbarrow, through 60mm core holes from the slab above. Each column took up to an hour to pour, with admixtures accelerating the hardening rate of this highly fluid 60MPa concrete. 

“There was no option but for concrete to be delivered in smaller volumes, otherwise the concrete would harden in the trucks before it could be used,” he says. “AfriSam worked closely with us to find a solution, which was to deliver just one cubic metre of readymix at a time.”

Readymix trucks usually carry six to eight cubic metres, so carrying just a fraction of this had severe implications for efficiency. However, the situation demanded flexibility from both partners, says AfriSam territory manager Melanie Ross, and the needs of the customer had to come first. 

“Also, the pours could only start in the afternoon, and often continued beyond the 18h00 deadline agreed between the contractor and the authorities,” says Ross. “So extended permissions were obtained, and the AfriSam-contracted drivers agreed to put in the extra time until pours were completed.”

AfriSam supplied over 9,700 m3 of readymix to the Old Cape Quarter project, and about 10 different concrete mixes for different applications. These came from the company’s Woodstock plant about 8km from site and its Peninsula Quarry plant at Durbanville.

HILTON HOTEL UPGRADES WITH GRUNDFOS PUMP SET

A Grundfos Hydro MPC-E booster pump set with four 7,5 kW motors and CIM 500 control system installed at the Hilton Hotel in Sandton is delivering both environmental and cost-saving benefits.

“The new energy efficient system has helped reduce our carbon footprint and combat climate change – an important part of our social responsibility,” says Charmaine Spasojevic, chief engineer at the Hilton Hotel.

Spasojevic says the cost saving will be achieved not only through the consumption of less electricity, but through reduced maintenance. This is due to the elimination of the separate variable speed drives (VSDs), meaning fewer items of plant to maintain. Management at the 12-floor, 329-room hotel will also have real-time access to operating data from the pump set. 

“The system integrates seamlessly with our building management system (BMS), allowing us full control over our service,” she says. The Grundfos CIM 500 control system allows the hotel to monitor various aspects of the pump set, including its running hours, energy consumption and discharge pressure, as well as any power supply problems or water shortages. 

According to Errol Dobson, Grundfos SA’s team leader building service, the Grundfos Hydro MPC-E maintains a constant pressure through continuous adjustment of the speed of the pumps. 

“The system’s performance is therefore adapted to the demand through the pumps being cut in and out as required, and through parallel control of the pumps in operation,” says Dobson. “Constant pressure control is also ensured through the continuous variable adjustment of the speed of each individual pump.”

The solution was designed and supplied in collaboration with Johan Truter, sales director at API Pumps Gauteng, and installed in June 2020. Grundfos service engineer Marius van Wyk commissioned the pump set, which will be serviced and maintained through a Service Level Agreement (SLA) with Grundfos.

DRY-TYPE TRANSFORMERS ENSURE SAFETY AT LNG CAMP

Dry-type transformers supplied by specialist company Trafo Power Solutions are ensuring the safe and reliable operation of substations in a construction camp at a large liquified natural gas (LNG) project in northern Mozambique.

According to David Claassen, managing director of Trafo Power Solutions, 18 dry-type transformers were included in modular substations built in South Africa and shipped to site recently. The company is in a strategic partnership with leading Italian transformer manufacturer TMC Transformers, and is competing at the highest level with other global OEMs.

“These substations are for the project’s first construction camp of about 9,500 contractors,”  Claassen says. “Our transformers have been specially designed for the high ambient temperatures in northern Mozambique.”

Ranging from 500 kVA to 1250 kVA, the temperature of these units will rise to a maximum of only 80⁰C when under full load. With Class-H insulation on both the medium voltage (MV) and low voltage (LV) windings, they will withstand a temperature of 180⁰C. This is considerably more than the potential 40⁰C ambient temperature in the tropics plus the 80⁰C temperature rise. The transformers are also designed for levels of humidity up to 95%.

He highlights that the safety advantages of dry-type transformers allow them to be used in this application. As they do not contain oil – which is the usual coolant in conventional transformers – they pose no fire, explosion or environmental hazard. 

“A transformer containing oil would present a significant risk in a construction camp accommodating thousands of people in close proximity,” he says. “The safety level of dry-type transformers also means that they can be used in enclosed spaces like modular substations. The minimal maintenance required is an added advantage, being located on such a remote site.”

Claassen notes that the global competition to supply this mammoth project has been intense, and points to the vital partnership between the local knowledge and experience of Trafo Power Solutions, and the technology and expertise of TMC Transformers.